USD - Water System Improvement - Phase I
BAI Number: 20921.01.01/OSE#R0609--06X
Bid Schedule: Unit Price Bid Schedule
Probable Construction Cost: $275,000.00 to $325,000.00
Deposit for Plans & Specs:
(Includes sales tax)
$21.20 (Electronic) - Non-refundable
 
Project Bid Date: 03/09/2010
Project Bid Time: 03:00 PM
Project Bid Location: Office of the State Engineer, Joe Foss building, 523 East Capitol, Pierre, SD 57501-3182
Project Deadlines: 08/15/2010 for substantial completion
09/15/2010 for final completion
 
Addendum Dates: 03/04/2010 Faxed - Click here to download
03/05/2010 Faxed - Click here to download

Scope of Work:
  • Replacement of 1200' of 6" water main and replacement of 1200' 8" water main, including all Demolition, General, and Civil work.
Contact Persons:
  • Justin Petersen, Banner Associates, Inc., (605) 692-6342, justinp@bannerassociates.com
  • Chad Bachman, Banner Associates, Inc., (605) 692-6342, chadb@bannerassociates.com