Lewis & Clark RWS: Centerville and Parker Service Lines
| BAI Number: |
20000.14.01 |
| Bid Schedule: |
Unit Price Bid Schedule |
| Probable Construction Cost: |
$3,500,000.00 to $4,500,000.00 |
Deposit for Plans & Specs:
(Includes sales tax)
|
$53.00 (Half-size) - Non-refundable
$21.20 (Electronic) - Non-refundable
|
| |
| Pre-Bid Meeting Date: |
09/09/2009 |
| Pre-Bid Meeting Time: |
02:00 PM |
| Pre-Bid Meeting Location: |
Lewis & Clark Regional Water System Office, 401 E 8th Street, Suite 306, Sioux Falls, SD, 57103 |
| |
| Project Bid Date: |
09/22/2009 |
| Project Bid Time: |
02:00 PM |
| Project Bid Location: |
Lewis & Clark Regional Water System Office, 401 E 8th Street, Suite 306, Sioux Falls, SD, 57103 |
| Project Deadlines: |
11/05/2010 for substantial completion
12/17/2010 for final completion
|
| |
| Addendum Dates: |
None
|
| |
| Additional Files: |
Geotek Report (08/26/2009)
Centerville Phase 1 Site Assessment (08/26/2009)
Parker Phase I Site Assessment (08/26/2009)
|
Scope of Work:
- Parker Service Line:
-
Approximately 72,742 linear feet of 10” diameter buried PVC pipe
-
Approximately 260 linear feet of 24” diameter jacked or bored highway crossing casing pipe
-
Centerville Service Line:
-
Approximately 26,525 linear feet of 6” diameter buried PVC pipe
-
Approximately 360 linear feet of 18” diameter jacked or bored highway crossing casing pipe
-
Work included in both Service Lines:
-
Miscellaneous appurtenances including direct bury gate valves, air relief valves and blow-off assemblies
-
Temporary and permanent erosion control, fencing, reclamation and seeding
-
Corrosion protection system components including galvanic anodes, coating and linings
-
Traffic control during construction
-
Pipeline hydrostatic pressure testing and disinfection
- and
Clean up and all other miscellaneous work required, not herein mentioned, but inferred from the construction contract documents.
|
Bid Documents:
Bid shall include all the sheets in "yellow" in the Specifications, including the following:
- (Follow Instructions to Bidders) Bid shall include (but may not be limited to) the following:
-
Representations, Certifications and Other Statements of Offerors (Form DI-2010)
-
Certificate of Nondiscrimination – Sheet CON-1
-
Elimination of Segregated Facilities – Sheet EOSF-1
-
List of Subcontractors, Suppliers, etc. (to be submitted within 48 hours after Bid Opening)
-
Bidders Statement of Qualifications
-
Bid Form and Bid Schedule
-
Bid Security – Either 10% Bid Bond or a certified check, cashiers check or bank draft in the amount of 5% of the total sum of the Bid
|
Contact Persons:
- Primary Contact – Scott Vander Meulen, Banner Associates, Inc, (605) 977-6342
-
Secondary Contacts – Kevin Kuebler, Banner Associates, Inc., (605) 692-6342
- and Tim Conner, Banner Associates, Inc., (605) 692-6342
|